aSc TimeTables - Constraints - Subjects This article is available in: There can be two math lessons on one day, but they need to be placed consecutivelly If you have 6 math lessons per 5 day week, then two will be on one day. In this case you can tell the software to place these consecutivelly: Add a new cardrelationships and select entries marked by red color:
But you can tell the software to place 6 lessons on 4 days. Or as shown on the picture you can let the software to decide if 6 maths will be on 4 days or 5 days. See also: I want to have 1+1+1+2 OR 1+2+2 lessons per week.
This article was viewed 99122 times.71885 / 99122
|